Organisations are not named. Figures are as recorded at the time.

Case study 1

Re-planning a network programme for a global investment bank

Delivery health check and recovery

The situation. A telecoms supplier had won a c.£16m programme for a global investment bank: a metropolitan area network link and the network fit-out of a new multi-storey building in London. The plan ran to about 250 lines, and the bank did not believe it was adequate for a programme of that size. The engineers were strong, but they worked in silos and nobody was leading them.

What I did. I spent nearly a week with the lead architect rebuilding the plan into twelve months and about 2,500 tasks, covering every phase from design and racking through configuration, testing and go-live to handover to support, down to every comms room. The supplier approved it first, then the bank.

The result. The bank had a plan it could believe and trust, and the programme was delivered almost exactly on time with over 20 engineers.

Case study 2

Setting delivery standards and a single intake for new work at a specialist NHS trust

Interim Head of PMO

The situation. The trust created a Head of PMO role at the start of a five-year, multi-million-pound digital strategy. The delivery function had three programme managers, each leading three project managers, across a £5m+ portfolio of projects ranging from about £50k to £2m. Board-level cuts later took the team from 14 people to six, with no change in what was expected of it.

What I did. I set new standards for delivery, risk and finance reporting and made each project manager responsible for their outputs. I built the framework for stage gating, prioritisation, and capacity and resource management, and designed a single gateway for new digital requests, where each one was screened for data, integration, supplier and data protection risk and then scored for priority. From 2024 I rebuilt the team to nine.

The result. The trust's digital board, attended by the deputy chief executive and the CFO, could see the health of the whole portfolio and a project-by-project view of finance, delivery and schedule. When I left, no project was red, about 20 to 25% were amber and the rest were green.

Case study 3

Taking routine work out of a PMO with tools the organisation already owned

Governance and reporting in Microsoft 365

The situation. A smaller team was running larger programmes. Project managers were spending hours each month preparing board reports, and PMO mailbox work took two and a half working days a week.

What I did. I reviewed the PMO's tools and replaced ServiceNow PPM and spreadsheets with a SharePoint portfolio system I built. I then added Power Automate flows, Power BI dashboards and about 30 Copilot agents inside the trust's existing Microsoft 365, with no extra licences or consultancy budget. I tested every agent myself, two project managers piloted the board-report agent before I released it to the team, and nothing went out without a person reviewing it.

The result. PMO mailbox work fell from two and a half working days a week to about two hours. Monthly board reports went from three or four hours to about 30 minutes, and half of the project administrator's time was freed for other work.